Why Greeley and Viola Are Closed at Rolling Road, and How West Springfield Gets Around Them

October 29, 2026

Since 9 a.m. on Wednesday, Oct. 21, drivers on Rolling Road have not been able to turn onto Greeley Boulevard. Six days later, Viola Street was closed off from Rolling Road too. Since summer 2025 the widening had kept to Rolling Road itself, with lane shifts and orange barrels. These two closures are the first time it has cut into the side streets. Both are at corners the finished road will change. Viola Street is the northern end of the new four-lane stretch. Greeley Boulevard is getting a traffic signal it has never had.

The two closures, side by side

The Virginia Department of Transportation announced each closure in its own release, and the reopening dates differ.

Closed segment Began Expected to reopen What's being built there
Greeley Blvd between Greenview Lane and Rolling Road 9 a.m. Wed., Oct. 21 By late November Western side of the intersection, where a new signal is planned
Viola St between Rolling Road and Flax Street 9 a.m. Tue., Oct. 27 By early December Eastern side of the intersection, at the north end of the widening

VDOT's Greeley Boulevard announcement gives the job about five weeks. Its Viola Street announcement also says about five weeks but expects the reopening "by early December." That puts Viola's reopening several days after Greeley's. If both stay on schedule, Thanksgiving week will be the last stretch with both closed at once.

Neither street is sealed off. VDOT says homes and properties on both closed segments can still be reached. You just can't get to them directly from Rolling Road, or onto Rolling Road from them.

The posted detours, turn by turn

Each detour follows streets that only people from the immediate blocks normally use, so here are the routes as VDOT posted them.

Greeley Boulevard, any direction:

  1. Stay on Rolling Road past Greeley.
  2. Turn onto Rivington Road.
  3. Take Greenview Lane back to Greeley Boulevard.

Viola Street from southbound Rolling Road:

  1. Turn onto Hunter Village Drive.
  2. Take Flax Street back to Viola Street.

Viola Street from northbound Rolling Road:

  1. Continue north on Rolling Road and turn onto Springfield Village Drive.
  2. Follow Brisbane Street to Bellamy Avenue.
  3. Return to Rolling Road heading south.
  4. Turn onto Hunter Village Drive, then Flax Street, back to Viola.

The northbound Viola route is the long one. It loops through Springfield Village to turn northbound drivers around, then sends them south to the same Hunter Village Drive entrance that southbound drivers use. Before you leave, you can check current conditions at 511.vdot.virginia.gov, on the free 511Virginia app, or by calling 511 from anywhere in Virginia.

The work zone switched sides, and the timeline grew

These closures land in the middle of the project. When the long-term lane shifts started the week of July 28, 2025, FFXnow reported that traffic from Hunter Village Drive/Tanworth Drive to Birmingham Lane would run on the east side so crews could build on the west side. From Birmingham Lane to Kenwood Avenue, traffic would run on the west side. FFXnow said the shifts were expected to last about a year.

VDOT's project page now describes the reverse. Traffic from Hunter Village/Tanworth to Birmingham runs together on the west side so crews can work on the east side. From Birmingham to Kenwood, traffic runs on the east side so crews can work on the west side. Both shifts are now listed as lasting until late 2027.

So the work zones have swapped sides, and the lane arrangement first billed for a year now runs to the end of the project. If you drive this road every day and the lanes seem to have moved under you since last year, they have. The Greeley and Viola closures fit the same pattern. Crews are rebuilding one side of each intersection at a time: the western side at Greeley and the eastern side at Viola.

The West Springfield Village civic association passed along the contractor's plan to its neighbors in March 2025. Medians would be paved temporarily to keep driveways and side streets reachable, one lane would stay open in each direction, and the grass medians would be rebuilt in the last stage. Sound walls would go up where the added traffic noise is expected to be noticeable.

Hidden Pond has a walking entrance this year

The closure at Greeley affects one of the neighborhood's most-used outdoor spots. Hidden Pond Nature Center is at 8511 Greeley Blvd., with woodland, trails, streams and its namesake pond. Drivers coming from Rolling Road need the Rivington Road and Greenview Lane detour this month.

There is now another way in. In a September 2026 status report, the Fairfax County Park Authority listed a new Pohick Stream Valley trail segment as complete. It runs 1,800 linear feet from Old Keene Mill Road to Hidden Pond Park, with asphalt and concrete paving, a new culvert and signage. It cost $583,000 from the 2016 and 2020 park bonds and was finished Dec. 30, 2025. That means the first time Greeley has been cut off from Rolling Road falls in the trail's first fall. For anyone within walking distance of Old Keene Mill Road, the walk avoids the detour entirely.

The nature center's calendar keeps going through the closure and past it. These programs are on the Park Authority's registration listings:

  • Fall Celebration, Saturday, Nov. 7, 1 to 2:30 p.m.: a fall foliage hike, a look at the waterways, and a craft to take home
  • Campfire Fridays, Nov. 13
  • Birding for Beginners, Nov. 15
  • Santa's Critters and Craft, Dec. 12
  • Night at the Nature Center, Dec. 16
  • Winter Solstice Bird Count, Dec. 20
  • Winter Survival Camp, Dec. 28 to 31

Both Dec. 6 Family Wreath Making sessions are already sold out. The Greeley intersection is expected to reopen by late November. If it does, the December programs will be reachable from Rolling Road again.

Errands and buses at either end

Most weekly errands from this stretch go to one of two shopping centers, and the closures change the route to each.

Up on Old Keene Mill Road, Old Keene Mill Shopping Center at 8424 Old Keene Mill Road has Trader Joe's, Walgreens, Planet Fitness, Kanji Sushi, McAlister's Deli, Honeygrow, Crimson Coward and Duck Donuts. Down Rolling Road, Saratoga Shopping Center at 8040 to 8092 Rolling Road has Giant, Starbucks, Saratoga Pizzeria, Hunan Taste, Firework Hibachi and Chipotle. If you live off Viola or Greeley, the first and last turn of each trip now go through Flax Street, Hunter Village Drive, Rivington Road or Greenview Lane.

Two Fairfax Connector routes use this road. Route 371 runs mostly along Backlick Road and Rolling Road between the Franconia-Springfield Metro/VRE station and the Lorton Park & Ride, and it lists Saratoga Shopping Center as a destination. Route 394 is the express bus from Rolling Road and Saratoga to the Pentagon Metro station, with the Saratoga Park & Ride among its stops. When this was written, Connector's operating status page showed regular service and no alert tied to these closures. Check it on the morning you ride. VDOT also warns that people on foot may find existing sidewalks and paths closed in the work zone.

Two seasonal dates near the corridor are worth adding to the calendar. Prince of Peace Lutheran Church at 8304 Old Keene Mill Road hosts the Finnish Christmas Bazaar on Saturday, Nov. 21, from 11 a.m. to 3 p.m. The Burke Lake Turkey Trot 5K and 10K runs on Thanksgiving, Nov. 26, at Burke Lake Park.

What the finished road adds, and when

When the barrels come down, about a mile and a half of Rolling Road between Viola Street and Kenwood Avenue will have four lanes instead of two. It will also get a raised median, a shared-use path, a sidewalk, a new traffic signal at Greeley Boulevard, an upgraded signal at Barnack Drive, and stormwater improvements. VDOT counts 16,000 to 19,000 vehicles a day on that stretch, all on a road that still has two lanes for most of its length. North of it, at the Rolling Road and Old Keene Mill Road intersection rebuilt in Phase 1 and finished in November 2021, Rolling Road carries 19,000 to 22,000 vehicles a day.

The contractor is Sagres Construction. In a February 2025 public presentation, VDOT gave the contract value as $42,975,040.84, with substantial completion on Oct. 22, 2027 and final completion on Dec. 2, 2027. VDOT's project page puts the whole two-phase project at $83 million, with $54.4 million set aside for Phase 2 construction. The two figures measure different things, the construction contract and the construction budget, but both point to about a year more of work after Viola reopens.

The Greeley closure will leave a lasting change. When the western side of that intersection reopens by late November, it will be one step closer to the signal it has never had. For the families who use Hidden Pond, that signal could end up mattering more than the extra lanes.

If you're thinking about selling a home near Greeley, Viola or anywhere along this stretch over the next year, the construction calendar affects when buyers can visit and how easy it is for them to get to your door. Katie Wojtowicz Homes can help you plan showings and a listing date around the detours, so buyers spend less time on the detour and more time inside the house. Let's Connect.